Lund Family Hall: Wally's & Wally's Market Renovation

Coming Soon: Wally's and Wally's Market

view of Wally's looking at service counter

view of dining looking towards market

A new dining space is coming to the corner of N. Portsmouth and N. Warren in Lund Family Hall! The new Wally's will have breakfast, lunch and dinner and convenient grab-and-go items. Stop by the new Wally's Market for pre-made food and convenience items, or study with friends in the light-filled dining space. 

Designed by Opsis Architecture, constructed by Colas Construction and operated by Bon Appetit, this project will be under construction for the 26-27 academic year. Check back here for project updates and our growing FAQ, The campus contact for this project is Associate VP for Campus Planning & Construction Jennie Cambier cambier@up.edu. 

Jump to FAQ

Jump to Feedback Form

Latest Updates & Impacts

 

November 2026

IN PROCESS

  • Below-slab and below-grade utilities roughed in. Plumbing work includes concrete core drilling (noisy).
  • Concrete will be poured before Thanksgiving week followed by starting framing of interior walls. Metal stud framing noise impacts include screw guns, chop saws and powder-actuated fasteners. 
December 2026
  • For finals week, the construction site will be intentionally quieter.
  • Finishing interior wall framing followed by concrete floor polishing.
  • Rough-in for HVAC, electrical, plumbing and fire sprinklers.
  • Roof work TBD for new mechanical units.
January 2027
  • HVAC and electrical rough in continues. 
February 2027
  • Roof work
  • Interior flooring
March 2027
  • Cabinetry install
  • Kitchen equipment install
April 2027
  • equipment commissioning 
  • punch lists
May 2027
  • furniture delivery
  • final completion

Recent Photos

trenches opened with backfill piles

concrete trench pour in process

FAQ

Q. Where is the project located?

A. The ground floor of Lund Family Hall

site plan

Q. What are construction hours? It's noisy here.

Construction hours are 8am-4pm Monday-Friday. It is possible that there will be impactful noise, and we will do our best to give residents a heads up when this will be happening. Look for email communication from the hall director. 

Q. When will the project be finished?

A. The project will be finished just after graduation in May 2027 but will not officially open to the UP community until August 2027 for the fall semester.

Q. What kind of food will Bon Appetit be serving?

A. The menu, based on feedback from students, includes a coffee bar, bagels, smoothies, sandwiches, salads and a rotating "build a bowl" station.

Q. Does Lund Family Hall access change for students?

A. No, there is no impact to Lund Family Hall access for students. The dining space has a separate entry and does not connect to the residential facility.

Q. Will contractors be inside Lund? 

A. It's possible you will see employees and subcontrators from Colas Construction inside Lund as they will need roof and basement access. They should not engage with students unless there is a safety-related issue. If you have any concerns please contact your hall director or the University's project representative Jennie Cambier cambier@up.edu 

Q. I have some feedback and other questions about the project. How can I get in touch?

A. Use the link below (anonymous or leave your name), or talk with your hall director if you have concerns or questions.

 

Submit Feedback and Questions